25 Aria Isle Dr · Lot 4 · The Woodlands, TX Foundation Decision Brief · REV 3 · 2026-06-15
Dunaway │ BEC · TBPE F‑1114 PROJ 12871.001 · ISSUED 06/15/2026 · ⊕ HOA PERMIT SET

The Foundation,
in three revisions.

A plain‑English read of Dunaway's REV 3 structural plans for 25 Aria Isle Dr, Lot 4. What's different between the two new REV 3 option sets, what changed from REV 2 — and how many piles go where, how the fill pad gets built, and what each path costs.

Engineer of RecordJuan M. Gonzalez, PE · #122348
Drawn / CheckedA. Wanzek (drawn) · J. Gonzalez (checked)
Each set18 sheets · S1.0 Plan + S2.0 Details
StatusHOA Permit — not for construction
Revision ladder · the title‑block history
07/11/25
Preliminary bid set
Review
07/25/25
70% set
Review
08/15/25
Issued for construction
04/06/26
HOA permit set
Rev 1
06/15/26
Reissued with two options — helical & straight shafts
Rev 3 · newest
00 / SUMMARY

The two questions, answered first.

If you read nothing else: REV 3 didn't redesign your house — it gave you a menu. Here's the short version of both comparisons.

Question 1 · The two REV 3 plans

Same house. Same slab. Two ways down to firm soil.

The Helical Piles set and the Straight Shafts set are identical everywhere except one thing: how the foundation reaches load‑bearing ground. Helical = steel piles screwed in. Straight shafts = drilled concrete piers, 24″/36″ wide.

→ A pick‑one bidding choice — steel piles vs. drilled concrete piers — not two different designs.

Question 2 · REV 3 vs REV 2 (last plan)

The “void box” is gone. A select‑fill pad took its place.

REV 2 floated a structural slab over a 6″ void box. REV 3 sets the slab on the ground, over a 24″ engineered select‑fill pad. REV 3 also adds the straight‑shaft option. Piles, grade beams, and all framing are unchanged.

→ Same structure, a simpler & typically cheaper slab approach, plus a second option to price.

01 / THE TWO PLANS

Helical Piles vs. Straight Shafts

Both are REV 3, both 18 sheets. A page‑by‑page text comparison shows the only sheets that differ are the Foundation Plan (S1.0) and Foundation Details (S2.0) — and even there, only the deep‑foundation element changes.

Fig. 1 — The only real difference: what carries the load downSECTION · NOT TO SCALE
Option A · Helical Piles
4″ SLAB‑ON‑GRADE GRADE BEAM 12×30 BEARING PLATE STEEL SHAFT HELIX PLATES ALLOWABLE 30 / 50 KIP · F.O.S = 2

Steel, screwed in. Designed & installed “by others” (the pile manufacturer). The plan lists two pile types by allowable working load — 30 & 50 kip — which, at the required 2× factor of safety, must each prove a minimum capacity of 60 & 100 kip. Embedment depth per the manufacturer's drawings. No spoils, fast, low vibration.

Option B · Straight Shafts
4″ SLAB‑ON‑GRADE GRADE BEAM 12×30 REBAR CAGE #3 TIES @ 12″ 24″ / 36″ Ø DRILLED ~15–18 FT BELOW GRADE *

Concrete, drilled. Cast‑in‑place piers, 24″ dia. (typical) and 36″ dia. Reinforcing scales with diameter (12″→4‑#4 up to larger→6‑#6), #3 ties at 12″ o.c. Familiar to local concrete crews; generates spoils and needs stable, dewatered holes.
* Depth — confirm: the plan carries two figures — a Foundation‑Parameters note of 18 ft below natural grade (U.N.O.) and a stray callout reading “12/36 drilled pier, 15'‑0″ below grade.” That 15′ note still appears on the helical sheet too; ask Dunaway which governs.

Element
REV 3 · Helical26‑0615 · Helical Piles
REV 3 · Straight Shafts26‑0615 · Straight Shafts
Slab system
Slab‑on‑grade, conventionally reinforced identical
Slab‑on‑grade, conventionally reinforced
Slab + barrier
4″, #4 @ 16″ o.c. each way · 10‑mil Class A identical
4″, #4 @ 16″ o.c. each way · 10‑mil Class A
Subgrade
24″ structural select‑fill pad + 4″ leveling bed identical
24″ structural select‑fill pad + 4″ leveling bed
Grade beams
12″ × 30″ · 4‑#4 top / 2 bottom · #3 ties @ 16″ identical
12″ × 30″ · 4‑#4 top / 2 bottom · #3 ties @ 16″
Deep foundation
Helical steel piles — by mfr. · allow. 30 / 50 kip → req. 60 / 100 kip differs
Drilled concrete piers · 24″ / 36″ Ø · ~15–18 ft · rebar cage + #3 ties
Sheets that change
S1.0 pile legend & capacity table; S2.0 pile‑to‑beam detail differs
S1.0 pier legend (Ø); S2.0 pier section + reinforcing schedule
Plain English · what it means for you

This is a bid decision, not a design fork. Dunaway drew the same house two ways so you can price both trades and pick the better value/schedule. Helical leans on a specialty pile installer (US Helicals, Cantsink, Ram Jack); straight shafts lean on a drilled‑pier / concrete crew. The slab, grade beams, and the whole building above are the same either way.

02 / HOW MANY · WHERE

Where the deep foundations go

You asked how many piles/piers and where. The honest answer: the same grid of points carries the house in both options — only the element at each point changes. The exact count and coordinates live on Dunaway's S1.0; the schematic below shows the pattern, not a survey.

Fig. 2 — Schematic deep‑foundation layout (plan view, looking down)ILLUSTRATIVE · NOT A SURVEY
≈ 151'‑6″ overall ≈ 90'‑6″ 30‑kip point (typ.) 50‑kip (heavier)

Read it as the pattern, not the exact count. Deep‑foundation points sit under the grade beams — at every intersection, at the steel‑column lines, and at intervals along each beam. For a footprint this size (≈151′ × 90′ ≈ 8,500 sf), a linear‑foot estimate — ~1,125 ft of grade beam at 8–10 ft spacing plus corners and the column / pool / elevator points — lands around ~125 points (range ~95–160). The exact number and coordinates are on Dunaway's S1.0 and get finalized on the pile contractor's signed shop drawing.

The useful insight

Helical and straight‑shaft use the same points. Because the grade‑beam grid is identical between the two REV 3 sets, the number and locations don't change — only the element installed at each point does (a steel helical pile, or a 24″/36″ drilled concrete pier). So whichever trade you pick, they're building to the same layout. To get the exact count: ask Dunaway for the pile/pier tally on S1.0, or have each bidder mark it on their takeoff — that's the number that should drive pricing.

03 / VS. THE LAST PLAN

REV 3 vs. REV 2

REV 2 (06/04/2026) was the previous plan — helical only, with a structural slab floated on a void box. Comparing it to REV 3‑Helical isolates exactly what Dunaway changed.

Fig. 3 — The headline change: how the slab sits over the claySECTION · NOT TO SCALE
REV 2 · was
STRUCTURAL SLAB VOID BOX — 6″ gap HELICAL PILE SLAB FLOATS OVER THE SOIL

Suspended slab. A 6″ collapsible void box sits between slab and clay, so when the soil swells it crushes the void instead of pushing your floor up. The piles carry the structure. More conservative; more cost.

REV 3 · now
SLAB‑ON‑GRADE 4″ SELECT FILL — 24″ + 4″ leveling bed HELICAL PILE SLAB RESTS ON ENGINEERED FILL

Ground‑supported slab. The void box is gone; the slab sits on a 24″ structural “select fill” pad (engineered, imported, compacted fill) over a 4″ leveling bed. Whether that 24″ requires excavating & replacing native soil or building a pad up on prepared subgrade is set by the geotech — confirm with Dunaway. Simpler, faster, typically cheaper than a void box.

REV 2 — removed / changed

What REV 2 had

  • Type: “Structural slab on void box w/ helical piles”
  • 6″ void box under the slab (V = 6″)
  • Vapor barrier: 10‑mil Class 1
  • Helical only — no straight‑shaft alternative
  • “Verify void box requirements with geotech”
REV 3 — added / changed

What REV 3 does

  • Type: “Slab‑on‑grade conventionally reinforced w/ helical piles”
  • 24″ structural select‑fill pad + 4″ leveling bed
  • Vapor barrier: 10‑mil Class A
  • Two option sets — helical piles and straight shafts
  • “Verify pad thickness & fill requirements with geotech”
Why this matters

Both designs answer the same problem — building on expansive Houston clay that swells and shrinks. REV 2 isolated the slab from the soil (void box); REV 3 conditions the soil instead (select‑fill pad) and sets the slab on it. The helical piles and grade beams are unchanged, so the building's structural backbone didn't move. A slab‑strategy change plus a new option — not a re‑engineering of the house.

04 / THE FILL PAD

How the select‑fill pad actually gets built

A fair confusion: “engineered fill” isn't poured like concrete — it's earthwork, built up in thin layers before the slab. And it doesn't automatically mean digging out your dirt. Here's the real sequence on site.

Fig. 4 — Building the select‑fill pad (auto‑plays · loops)SECTION · NOT TO SCALE
FIRM BEARING SOIL EXPANSIVE CLAY · native EXPANSIVE CLAY · native REMOVE SOFT / ORGANIC SOIL SELECT FILL SELECT FILL · 6–8″ LIFTS LAB ✓ 24″ 4″ SLAB‑ON‑GRADE

 

1

Strip & prep

Clear the building pad and remove organics / soft soil down to the depth the geotech report calls for. This is the step that may (or may not) mean over‑excavating native clay — the report decides.

2

Import select fill

Truck in lab‑approved “select fill” — soil chosen to a spec (a controlled, low‑plasticity gradation), not whatever is on site.

3

Spread in lifts

Place it in thin layers (“lifts”), typically 6–8″ at a time — you don't dump 24″ at once.

4

Compact & test

Roll each lift to a target density (e.g. ~95% Proctor). A testing lab signs off every layer before the next — this is the “subgrade / material testing” the plan defers to the geotech.

5

Build to 24″ + bed

Repeat until the 24″ pad reaches design grade, then a final 4″ leveling bed to set the slab elevation.

6

Piles, then slab

Helical piles or drilled piers go through the pad to firm soil; then grade beams and the 4″ slab pour on top. The pad supports the slab; the piles carry the house.

So — do you have to replace soil?

Not automatically. The structural sheet only says “24″ structural select fill” and points to the geotech for the rest. On high‑plasticity clay, geotechs often do call for some over‑excavate‑and‑replace (sometimes deeper than 24″), but it can also be a built‑up pad on prepared subgrade. One clean question closes it: ask Dunaway / Quartet — “for the REV 3 select‑fill pad, how much native soil is removed vs. built up, and to what depth?” That answer also drives the dirt‑work cost.

05 / COST & TIME

What each path costs — and how long

Researched market ranges for the deep‑foundation element only (slab, pad, and grade beams cost roughly the same either way). These are sourced estimates, not bids — use them to frame the conversation, then have your bidders price Dunaway's exact pile/pier schedule.

Option A · Helical Piles

Steel, screwed in

~$150k–$200ktypical · range ~$70k low → ~$320k high
Per pile, installed~$700–$2,000
Install on site~1–3 weeks
5–8 days w/ 2 crews
Concrete cure waitNone — load immediately
Schedule riskLow · weather & water tolerant
Option B · Straight‑Shaft Piers

Concrete, drilled

~$375k+typical · range ~$170k low → ~$720k+ high
Per pier, installed24″ ~$2–3.2k · 36″ ~$4.5–6.5k
Install on site~2–4+ weeks
+ 5–10 day cure
Groundwater adder+25–75% on cased shafts · spoils $15–45k
Schedule riskHigh · rain + clay stops drilling
Bottom line — for THIS site

On expansive clay with groundwater above 7 ft and a schedule‑sensitive steel frame, helical piles are typically both cheaper and faster — on the order of 40–55% less (≈$170k vs ≈$375k+ typical, before the casing & spoils adders groundwater triggers) and ~1–3 weeks faster net, mostly because there's no concrete cure and the steel frame can land the day piles finish. It flips toward drilled piers only if Dunaway uses large‑diameter shafts to cut the point count, the site can be kept dry/uncased, or per‑point loads exceed practical helical capacity.

The count that drives both numbers

Both estimates assume ~125 support points (range ~95–160) — from ~1,125 lf of grade beam at 8–10 ft spacing plus corners and the heavier column / pool / elevator points. That's the same ~125 points in the layout schematic above, whichever element fills them. Get the real count from Dunaway's S1.0, have each bidder price that exact schedule, and require the concrete bidders to quote dry vs. cased/slurry below 7 ft separately.

Estimates compiled from published 2024–26 market data (HomeGuide · TorcSill · Hubbell/CHANCE · Helical Pile World · Houston ready‑mix & Texas eng‑forum contractor data) — not quotes. Largest uncertainties: the structural 30–50 kip helical unit price and the groundwater casing premium. Bidders to price against — helical: TorcSill, US Helicals, Cantsink, Ram Jack Houston; concrete: Lane, DSD, Volcano.

06 / STEADY

What did not change

A full text diff of all 18 sheets confirms the changes are surgical — confined to the Foundation Plan and Details. Everything below is identical across REV 2, REV 3‑Helical, and REV 3‑Straight.

Sheets 4–18 — framing, roof, schedules, shear walls Grade beams · 12″ × 30″ · 4‑#4 / 2 bot · #3 ties @ 16″ Helical capacities · allow. 30 / 50 kip · F.O.S 2 Slab thickness · 4″ Slab dowels · #3 @ 12″ o.c. Engineer & seal · J. Gonzalez PE #122348 Project geometry & column grid Deep‑foundation locations (same both options)
07 / DECODER

The terms that carry the whole story

Kip
An engineer's unit of force: 1 kip = 1,000 lb (a “kilo‑pound”). A “30‑kip” pile is rated to carry 30,000 lb. Just shorthand to keep big load numbers short on the drawings.
F.O.S = 2
Factor of Safety. Each pile must hold twice its working (allowable) load before it's considered at capacity. So the 30 & 50‑kip allowable piles must each prove a minimum capacity of 60 & 100 kip.
Void box
A collapsible cardboard “carton form” placed under a slab or beam. On swelling clay it gives the soil somewhere to expand — it crushes instead of lifting the structure. Used in REV 2; removed in REV 3.
Select fill / “engineered fill”
Imported, lab‑tested soil (controlled gradation, low‑plasticity) placed and compacted in thin lifts to a known strength — “engineered” because it's built to spec. REV 3 sets a 24″ pad. It does not necessarily mean digging out 24″ of your dirt — removal‑and‑replace or a built‑up pad; the geotech decides.
Helical pile
A steel shaft with screw‑like helix plates, turned into the ground by machine. Capacity confirmed by install torque. Fast, no spoils — designed & installed by a specialty contractor (“by others”).
Straight‑shaft drilled pier
An augered hole (24″ or 36″ across) filled with a steel rebar cage and concrete. Conventional and familiar to local crews — but it produces spoils and needs a stable, dry hole. (Depth: plan shows both 18 ft and a stray 15′ note — confirm.)
Grade beam
A reinforced concrete beam that ties the foundation together at ground level and spans between the piles/piers, carrying the walls above. Here: 12″ wide × 30″ deep — unchanged in every revision.
U.N.O. / TYP.
Drafting shorthand: U.N.O. = “unless noted otherwise,” TYP. = “typical” (applies to all similar conditions). “24″ pier, TYP.” means 24″ everywhere except where a different size is called out.
Open items to close with Dunaway

All three sheets are stamped “Issued for HOA Permit Set — NOT for construction.” Before bidding, confirm: (1) the governing pier depth (18 ft vs. the stray 15′ note); (2) the select‑fill scope — remove‑and‑replace vs. built‑up, and to what depth; (3) the pile/pier count on S1.0; and (4) which option — helical vs. straight shaft — you'll build. Pile/pier sizing is still “designed by others.”